WHAT IS MTO, BOM AND BOQ?

WHAT IS MTO, BOM AND BOQ?

PIPING MTO

~MTO stands for material take-off.

~MTO of the piping item is a detailed listed piping component for the given project.

a. code b. size c. quantity d. purchase department

1-"piping material take off"----

I need fabrication, purchase, and or some construction for the action of counting the pieces and part

2-"bill of material"-not used for purchasing

listing of only the material shown on individual specific drawings such as piping isometric

the piping and components will have already been purchased and readily available for fabrication

3-"bill of quantity"-it is tendering document

totaling all the quantity from all the BOM from the whole project

*purpose MTO

making proposal

material estimation

preparation of purchase requisition

*MTO stage

there are 3 stage of MTO stage

  1. preliminary

  2. secondary

  3. final stage

    1. preliminary stage: 30% 50% 70% 90% final

    ~ is generated manually at beginning of project

    ~Generated the mto based on p and id and project specification

    ~ never used for purchase reason

    * Reason for preliminary MTO

    A. Assist with order to magnitude(+_10 %) estimate for the project

B. Order to magnitude RFQ Request for a quote for piping Material

NOTE :

P and ID : ready for client review and approval

plot plan : approval by the client

*DOCUMENT FORPRELIMINARYY MTO

a. p and id

b line list

c piping material specification

d project specification and standard drawing

e equipment drawing and datasheet

f instrument hookup SketchUp

STEP FOR MTO

COLLECT ALL THE MTO DATA

ALL PICKABLE ITEM LISTED ABOVE THE FIGURE

ALL NON PICABLE ITEMS ABOVE THE FIGURE

*STAGE 2 SECONDARY

TO update the piping quantity for the issue of an actual purchase order for piping material

to update the project estimate procurement of piping material

*stage 3 FINAL

identify any late addition to the project and approve by client

~some instrument items not consider MTO list like control valve, psv , tagged instrument part

~not listed breakup flange in MTO